Tolent Construction

Main Contractor – Tolent Construction

Value – £400,000

Hot Rolled Steel – 220 T

Cold Rolled Purlins/Rails – 25 T

This included erecting a free standing mezzanine floor within the building once the new structural slab had been poured, no cranes to erect all carried out using a telescopic telehandler.